Tag Archives: progress_energy

Sally, Kirk and Shearon-Harris

Following up on my post Shearon-Harris Offline: Who Tripped Over the Wire?, I’d like to direct your attention to two of our wonderful local ‘bloggers.

Sally Greene has two great posts on the Shearon-Harris nuke plant safety issues and the resulting spin.

First, FAIRWarning

Tonight I went to the briefing in Pittsboro on the Shearon Harris nuclear power plant, its serious and repeated fire safety violations, and the legal action that was taken today by NC WARN, the Nuclear Information and Resource Service, and the Union of Concerned Scientists to seek an emergency enforcement action from the NRC.

Second, today’s absolutely wonderful deconstruction of Progress Energy’s spin, in Shearon Harris: beneath the spin

In response to this week’s events, the community relations manager of Progress Energy was kind enough to write yesterday in an effort to persuade me that the Shearon Harris plant is safe and law-abiding. But I am sorry: this version doesn’t fit the facts. Here is Mr. Clayton’s memo, annotated by Pete MacDowell of NC WARN.

The sharply observant Kirk Ross (Exile, Cape Fear Mercury) follows the money in his post from Exile on Jones Street (why “on”?) titled Duke wants you to pay for a plant they may never build

Duke Energy and Southern are working on a new Nuke project in Cherokee County S.C. No permits have been issued, no construction work on the plant has started. They won’t even submit a request to the NRC for another year at the earliest. In fact, the plan is for the plant not to be online until 2016. Then, there’s the whole idea that a new nuke is really going to happen. Some folks like ‘em. Some folks don’t. Some folks really, really don’t.

Shearon-Harris Offline: Who tripped over the wire?

Local Progress Energy nuke plant Shearon-Harris went unexpectedly offline (or in nuke industry jargon “had an unplanned outage”) this morning:

Progress Energy’s Shearon Harris nuclear plant shut down today at about 10 a.m., in the first unplanned outage this year.

The nuclear plant, about 25 miles southwest of Raleigh, turned itself off automatically when the plant’s generator stopped working. Plant personnel are trying to determine the cause of the malfunction.

N&O

Progress Energy continues to have legal, technical and regulatory problems with Shearon-Harris and other operations, including whistle-blowing by security guards, issues with their plan to build additional on-site capacity (reactors) and, of course, the wondrous new over-charging meter fiasco.

Incredible timing as tomorrow (Sept. 20th), NCWarn, our local safe-nuke activists, are holding a meeting on Shearon-Harris’ fire violations.

Community Briefing
Emergency Action on Fire
Violations at Shearon Harris Nuclear Plant   

Wednesday. Sept 20, 7 pm
Central Carolina Community College,
Multi-purpose Room, Hwy 64 West, Pittsboro


Click here for more information [PDF]